Budgets: Show time tracks for Work Items/Iterations assigned

Gathering Feedback

Comments

1 comment

  • Avatar
    Leah Copeland

    Hi Mark!

    As the functionality currently works, when you assign an iteration or item to a budget, all time records are counted into this budget, but are not displaying on the Budgets page. Also, all children items are counted into same budget until you explicitly exclude any child from counting (right side of the page).

    To see all time tracks for a specific budget, you can navigate to Times Explorer page and filter by the Budget column (and then group by work items/Iterations.

    Does that help?