Allow work item budget inheritance with different iteration paths

Officially Answered

Comments

1 comment

  • Avatar
    Andrea Moro

    Hi Michael

    if I understand this correctly, your task is not inheriting the budget from its parent work item because they are in different iterations. This is by design, the idea being that if you assign an iteration to a budget then that becomes the criteria we use to define what work should count against that budget. For a budget to be inherited from the Epic to the Task level, regardless of the iterations, you would need to assign it to the Epic itself. Would that be a viable option for you?

    Kind Regards,

    Andrea
    Product Owner - www.7pace.com